Contract Administration
Projects · Henderson Creek Outfall · Contract Admin
Variations 5
Pending VAR-014 — Shoring system upgrade
In review VAR-013 — Pipe diameter alignment
Approved VAR-012 — Topsoil import
Rejected VAR-011 — Extended working hours
RFIs 7
Awaiting RFI-022 — PS H4A chainage
Engineer RFI-021 — Manhole upsize query
Closed RFI-020 — Survey tolerance
Engineer RFI-019 — Concrete cover